Amtrak audit faults D.C. station project
July 31, 2018 Commuter/Regional, High Performance, Intercity, News, Passenger
Amtrak audit faults D.C. station project
Written by Mischa Wanek-Libman, Editor, Railway Track & Structures; and Engineering Editor, Railway Age
Amtrak rendering of the Washington Union Station improvement project.
Amtrak will improve its project management processes concerning a series of projects at Washington Union Station following an audit by the Amtrak Office of Inspector General (OIG) found the projects were at risk of delays and cost overruns.
The Amtrak OIG audit warned a series of near-term projects, which were part of the larger Washington Union Stations 2nd Century Plan, could be at risk of delays and cost overruns due to what the audit called weaknesses in their scheduling, cost estimating and project management practices.
According to Amtraks Northeast Corridor website, the Washington Union Station projects are designed to triple passenger capacity and double train capacity over a 20-year period at the railroads second busiest station. ... The Amtrak OIG recommended that Amtrak use its Enterprise Program Management Office standards and other commonly accepted project management standards such as project charters, an integrated master schedule, well-supported cost estimates and risk mitigation plans.
In response to a draft of the audit, Amtrak agreed with the recommendations and outlined a schedule to address them. Amtraks timeline for the implementation ranges from August 2018 to January 2019 depending on the task. ... For more information, see the
Amtrak OIGs audit report.