Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News Editorials & Other Articles General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

TexasTowelie

(117,040 posts)
Sun May 6, 2018, 11:40 PM May 2018

SCANA official openly doubted nuclear project would finish on time, former Westinghouse managers say

COLUMBIA — A SCANA official overseeing work on the V.C. Summer nuclear project openly doubted the reactors would be finished on time, saying in meetings the pace was on track to finish years behind schedule, according to a lawsuit filed in federal court and records obtained by The Post and Courier.

The concerns came up in monthly meetings about the project’s construction progress when SCANA’s contractor Westinghouse Electric told the power company how much headway it was making.

Month after month, it reported sluggish results that put the project further behind.

More than once, a SCANA employee pointed out the anemic pace made the schedule unrealistic, according to a lawsuit filed against SCANA by its Wall Street investors.

Read more: https://www.postandcourier.com/business/scana-official-openly-doubted-nuclear-project-would-finish-on-time/article_b25ce48e-4dff-11e8-9210-a7619a1687e4.html

Latest Discussions»Region Forums»South Carolina»SCANA official openly dou...